Project Overview

Detailed engineering survey, cadastral mapping, soil testing, departmental permissions for 600 Km IOCL pipe line route – Durgapur to Barauni (via Masudanpur), Gidha (Patna) – Muzzaffarpur, work is under completion stage, through substantial work had been completed for detailed engineering and soil testing.

 

Services Provided
  • Reconnaissance Survey
  • Detailed Engineering Survey
  • Population Density Index Survey
  • Soil Resistivity Survey
  • Soil Chemical Analysis Survey
  • Soil Stratification Survey
  • Data Generation Survey
  • River hydrological data collection/ generation
  • Cadastral Survey
  • Technical Report Preparation
  • Topographical survey at station locations
  • Geotechnical investigation at Station locations and HDD crossing locations
  • Providing services for establishing Right of User (ROU) in Right of Way (ROW) under P&MP Act, 1962
  • Obtaining approvals/ permissions from the respective State/ Central and other Statutory Authorities
  • Providing support services for forest clearance under Forest Conservation Act 1980 and Forest Right Act 2006
  • Providing Services related to opening of Right of Way (ROW) and other activities for the entire final proposed pipeline